| # | Item | Quantity |
|---|---|---|
| 01 | Internal Painting Surface preparation, cleaning, minor crack/defect filling, 2 coats of wall putty, 1 coat of interior primer and 2 coats of interior emulsion paint, including sanding between coats, necessary touch-ups and complete finishing as per approved shade/sample and manufacturer's recommendations. OptionsPer FLat Rate | 1 ls |
Payment terms will be on milestone Basis Work timing should be 8.00am to 8.00Pm Safety and compliance: • All workers wear safety helmets, safety shoes and reflective jackets on site • A first aid kit is kept at the work location • All electrical work complies with the Indian Electricity Rules 2005 • The contractor gets the permits and clearances needed • Accidents or injuries are reported to the site supervisor at once Payment terms: • 20% advance when work starts • 30% at 50% completion (verified by the site engineer) • 40% at 90% completion • 10% retention, released 30 days after completion Payment within 7 working days of an invoice with work completion certificates.